Macallan Overton Warehousing Complex
Comprehensive transformation of the Macallan Estate, providing sixteen high-capacity warehouses and fully integrated production and operation facilities.

| Client | The Edrington Group |
| Location | Aberlour |
| Services | Cost Consultancy |
Located within the existing Macallan Estate, the maturation warehouse complex was developed to support Macallan Distilleries’ expanding production needs. Due to the scale of the project, construction was delivered over multiple phases.
Extensive earthworks were undertaken to prepare the site, with more than 1,500,000m³ of soil relocated to form the required development platforms. The completed complex comprises of sixteen racked warehouses, each providing 6,000m² of space and configured into three 2,000m² storage cells.
Additional facilities including a disgorging and filling store, cooperage, amenities building and office accommodation were also constructed, completed by both hard and soft landscaping and associated infrastructure.